Wood Hollow Drainage Improvements Project

Engineering project details, documents, and contact information can be found below.

Wood Hollow Drainage Improvements Project

Project Information

Project Name
Wood Hollow Drainage Improvements Project
Project Type
Structural
Project Manager
John Kahle
Consultant
Bowen Collins & Associates
Estimated Bid Documents Available
February 2026
Construction Contract Date
3/11/2026
Bids Due
2/23/2026 3:00 PM
Estimated Construction Cost
$300,000

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

2/23/2026 - Bid Results

On February 23, 2026, at 3:00pm, bids were received for the Wood Hollow Drainage Improvements project. The bid opening sheet is available on the JVWCD website. The apparent low bidder is Newman Construction. This project will be presented to the JVWCD Board of Trustees on March 11th for consideration to award the project.

2/18/2026 - New Addendum

Addendum #1, answering final questions from contractors, is now available from the JVWCD website. The bid due date and time remain 3:00 pm on February 23, 2026.

2/2/2026 - Bid Documents Available

Bid documents for the Wood Hollow Drainage Improvement Project are now available on the Jordan Valley Water Conservancy District Webpage. Bids are due on February 23, 2026 at 3:00 pm.

Contract Documents and Project Information

Date Type Description Download
2/23/2026 Bid Results Bid Results Download
2/18/2026 Addendum Addendum #1 Download
2/3/2026 Attachment Referenced Documents Attachments Download
2/2/2026 Bid Documents Specifications Download
2/2/2026 Bid Documents Bid Documents Download
2/2/2026 Drawings Drawings Download