Terminal Reservoir Gearbox Replacement Basin 3
Project Information
Project Name
Terminal Reservoir Gearbox Replacement Basin 3
Project Type
Reservoir
Project Manager
Jake Slater
Project Description
Replace three (3) butterfly valve gearboxes in basin 3 of Terminal Reservoir.
Consultant
JVWCD
Bids Due
10/23/2025 2:00 PM
Contact/Planholders List
This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.
Public Notices
10/20/2025 - New Addendum
Addendum No. 1 for the Terminal Reservoir Gearbox Replacement Basin 3 project is now available on the JVWCD website.
10/3/2025 - Bid Documents Available
The bid documents for the Terminal Reservoir Gearbox Replacement Basin 3 project are now available on the JVWCD website.
Contract Documents and Project Information
Date | Type | Description | Download |
---|---|---|---|
10/20/2025 | Addendum | Summary of Addendum No. 1 Changes | Download |
10/20/2025 | Addendum | Addendum No. 1 Bid Docs. | Download |
10/3/2025 | Bid Documents | Bid Docs | Download |