Jordan Aqueduct, Reach 4 Blow-Off Drain
Project Information
Project Name
Jordan Aqueduct, Reach 4 Blow-Off Drain
Project Type
Pipeline
Project Manager
Conor Tyson
Project Description
Attach to an existing blow-off line and construct a new PVC pipeline about 700 feet from existing blowoff to a UDOT storm channel.
Consultant
JVWCD
Estimated Bid Documents Available
August 2025
Bids Due
9/11/2025
Estimated Construction Cost
$90,000-180,000
Contact/Planholders List
This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.
Public Notices
8/29/2025 - Bid Documents Addendum
Addendum #1, answering questions and providing additional information requested at the pre-bid meeting, is now available on the website. The bid due date and time remain unchanged.
8/27/2025 - Announcement
The sign in sheet from the pre-bid meeting held on August 27th, 2025, is now posted on the JVWCD webpage.
8/20/2025 - Bid Documents Available
Bid documents for the Jordan Aqueduct, Reach 4 Blow-off Drain Project are now available on the Jordan Valley Water Conservancy District Webpage. Bids are due September 11th at 4:00 pm
Contract Documents and Project Information
Date | Type | Description | Download |
---|---|---|---|
8/29/2025 | Addendum | Addendum #1 | Download |
8/27/2025 | Planholders List | Pre-Bid Sign in | Download |
8/20/2025 | Bid Documents | Bid Documents | Download |
8/20/2025 | Drawings | Bid Drawings | Download |
8/20/2025 | Bid Documents | Technical Specifications | Download |